The national government has published a list of development projects for Western Kenya, covering roads, affordable housing, healthcare, water, agriculture and industrial parks. Tuko puts the package at about KSh 40 billion.

The projects span Kakamega, Vihiga, Bungoma, Busia and Trans Nzoia counties. They are set out in a development report compiled through the Office of the Prime Cabinet Secretary ahead of President William Ruto's planned tour of the region, according to Tuko.

The administration says the works are in line with its Bottom-Up Economic Transformation Agenda (BETA).

Roads take a large share

Road construction makes up a significant part of the planned spending. Kakamega has several major projects under way:

  • The 43-kilometre Kakamega-Navakholo-Musikoma Road, at KSh 2.84 billion
  • The 36-kilometre Turbo-Shikhendu Road, valued at KSh 3.67 billion
  • The 22-kilometre Malava-Samitsi-Navakholo Road, costing KSh 1.63 billion
  • The 19-kilometre Kakamega Airstrip-Chepsonoi-Shinyalu Road

In Bungoma, the 41.1-kilometre Musikoma-Buyofu-Mungatsi-Myanga-Mateka road is reported to be 75% complete. The project is worth KSh 1.96 billion.

Busia's road works include the Nangina-Sio Port-Okados-Mundere Road, at KSh 860 million. The county is also getting the Matayos-Namwitsula Bridge-Nasewa-CAIP-Shibale road, valued at KSh 545 million.

Prime Cabinet Secretary Musalia Mudavadi spoke in Kakamega. He said the administration had committed to building 1,000 kilometres of tarmac roads across the region. According to him, the pledge came out of negotiations held before the 2022 General Election.

Housing and hospitals

The report says 440 affordable housing units have been completed and commissioned in the region. More than 10,000 units are under construction or in procurement.

In Busia, the Nasewa Affordable Housing Project aims to deliver 2,000 units at an estimated KSh 5.5 billion. Kakamega is running a wider housing programme valued at KSh 14 billion.

In health, the upgrade of the Kakamega County Teaching and Referral Hospital to Level Six status is said to be 85% complete. Funding has also been approved for a proposed Level Six hospital in Bungoma.

Water, industry and sugar

Three water projects are listed:

  • The KSh 469 million Alupe Dam in Busia
  • The KSh 289 million rehabilitation of Namuninge Dam in Bungoma
  • The KSh 212 million Shitoli Water Project in Ikolomani, expected to serve more than 45,000 residents

County Aggregation and Industrial Parks are planned at Nasewa, Sang'alo and Sinoko. The Nasewa park alone is estimated at KSh 500 million.

The government also says it is supporting the revival of the Mumias and Nzoia sugar factories. Both are long-standing pillars of the region's cane-growing economy.

The Sinoko irrigation project in Navakholo covers about 1,000 acres. It is reported to be 80% complete and is expected to benefit around 2,000 farmers.

Re-election appeal

Mudavadi used the Kakamega event to rally support for the President ahead of the next election. He urged Western Kenya residents to back Ruto's bid for a second term.

"Give him a second term to consolidate these gains." – Musalia Mudavadi, Prime Cabinet Secretary

The project list comes as the President prepares to tour the region. Dates for the tour were not given in the report.