John Kamau is about 60 years old, and he says that in all that time no vehicle has been able to use the 13-kilometre track that links his village to Kanyenyaini in Murang'a's tea country. Now MPs have stood on that same road and told the contractor hired to tarmac it that the excuses have run out.

The National Assembly Committee on Transport and Infrastructure, led by chairperson and Ndia MP George Kariuki, toured sections of the Mau Mau Roads Lot 2 project in Kangema and Kigumo constituencies and found the work behind schedule. The committee's verdict was blunt: money is not the problem.

"We can confirm that the contractor has been paid in full, and we have directed the immediate redeployment of the workforce from the other ongoing projects to ensure that Kanyenyaini-Tuthu road construction is accelerated and completed within the stipulated timelines," Mr Kariuki said.

What the committee ordered

According to the Kenya News Agency and The Standard, the MPs issued a series of directives after meeting the contractor on site:

  • Workers and equipment are to be moved from other projects to the Tuthu-Kanyenyaini road in Kangema
  • Work on the 20-kilometre Kangema-Karurumo stretch is to begin in January 2027
  • In Kigumo, the section running through Kinyona, Kangari and Kigumo wards is expected to be finished by mid-2027
  • The contractor is to keep repairing sections damaged by the ongoing rains so residents can still get through

Jomvu MP Twalib Bady, a member of the committee, told residents the road would be tarmacked "without further delays", saying tea, dairy and avocado farmers could not prosper without it.

Why residents blocked the site

The visit followed a standoff two months ago, when residents along the Tuthu-Kanyenyaini road blocked the contractor's site over claims that bitumen was about to be moved to another section of the project.

Kangema MP Peter Kihungi said the community had since agreed that nothing would leave the site until the road is done. "A while ago it was reported that materials and equipment were being relocated to construct roads in other areas, and the residents joined hands and rejected any site relocation until this Kanyenyaini-Tuthu road is tarmacked," he said.

Kigumo MP Joseph Munyoro said people in his constituency expected the contractor to finish on schedule so that they could see value for their taxes.

'Our tea earnings suffer'

For farmers, the cost of the delay is counted in lost income. Resident Rhoda Njeri said getting produce to market was "an exercise in futility" and that low tea earnings in the area had been blamed on the lack of a road. She noted that materials used to build roads elsewhere are sourced from the locality while their own road remains in a deplorable state.

"We have received many promises before, yet our road remains impassable, but we are now hopeful that it will finally be tarmacked," Mr Kamau said.

The bigger project

The Mau Mau road project is named in honour of Kenya's independence fighters and is meant to shorten journeys and ease the movement of goods between four Mt Kenya counties. The Standard reports that the full network of main arteries and feeder roads runs to about 540 kilometres across Kiambu, Murang'a, Nyeri and Nyandarua, with 225 kilometres of it in Murang'a.

Mr Kariuki said the government was committed to completing all stalled projects across the country. For Kangema, the first test of that promise comes in January.