Mutua Mutia was a young boy when his family moved into Buxton estate in Mombasa. His firstborn is now past 30, and seven years after he was told to move out for "one year", he is still waiting to go home.

"We were evicted with the promise that we would return after one year, but today it is seven years and we are still struggling," Mutia told The Standard.

His frustration sits at the centre of a widening row over Buxton Point, the affordable housing project built on the old county estate by GulfCap Real Estate under a joint venture with the Mombasa County government.

Stop-work order turns violent

On November 10, the county issued an enforcement notice ordering the developer to halt work on Phase 2, citing construction under a varied plan without county approval and the dispute with former tenants. Lands, Housing and Urban Development CEC Mohamed Hussein told former tenants at Tononoka Hall that the developer had not handed over the county's 10 per cent share of units, a rebuilt ECDE centre or a community social centre, the Kenya News Agency reported.

When county officers went to serve the notice the next day, they were allegedly pelted with stones at the site. "Let them bring goons, machetes, and stones if they want. I am not intimidated," Hussein said.

'Evasive drama'

On Thursday, Haki Yetu, Jamvi la Ardhi na Makao Mombasa Forum and Coast Land Non-State Actors said the tenants were being forgotten in the fight. "It is a matter of life and death, a matter of survival," Haki Yetu executive director Peter Kiama told The Star, calling the confrontation "evasive drama" aimed at escaping accountability.

The groups want:

  • The joint venture agreement between the county and the developer published.
  • Records of who owns the land under the project made public.
  • 522 units allocated to former tenants under a tenant purchase scheme, as the Senate recommended.
  • An account of deposits withheld from the relocation fund, and the interest earned.
  • The EACC to release its findings on the status of the land.

Haki Yetu legal officer Munira Ali accused politicians of using the issue because "elections are close".

'Not asking for free houses'

Former tenants say each household received Sh240,000 to rent elsewhere for 12 months, plus a promised Sh60,000 deposit towards a new unit that many say they never got. "What we received was relocation money, not compensation for our houses," said Mohamed Mzee Rubea, chairman of the evicted residents. Jamvi la Ardhi chair John Tsuma said they want to buy the houses, not get them free.

GulfCap chief executive Chris Ochieng has denied any wrongdoing, saying all documents are open to scrutiny. He said 492 units will be handed to buyers by December, that the county's 10 per cent share will be transferred when the project is complete, and that the dispute threatens hundreds of jobs. "It is very unfortunate that Mombasa County officials are bringing politics into a national project," he said.

Phase 1 delivered 584 homes in 2023. Phase 2 is meant to add about 1,400 to 1,500 more by August 2027.

Photos: The Star / Brian Otieno; The Standard / Robert Menza. Thumbnail design: HAMASTA MEDIA.