The National Land Commission (NLC) has pushed back against criticism over delayed compensation of landowners on the Isiolo-Mandera highway. It says the Kenya National Highways Authority (KeNHA), not the commission, processes and pays out the money.

The commission responded in a statement on Wednesday, November 18, according to Kenyans.co.ke. The statement followed concerns from the World Bank that slow land compensation was holding up the 740-kilometre road and pushing up its costs.

NLC outlines its limited role

According to the NLC, its mandate on the project is restricted to valuing land, verifying assets and drawing up compensation schedules. Processing funds and disbursing them to Project Affected Persons (PAPs) falls to KeNHA, in line with a World Bank directive under the Horn of Africa Gateway Development Project (HOAGDP).

The commission said it was clarifying media reports on what it described as "alleged delays" in valuation and compensation under the project.

World Bank warns of mounting costs

The concerns were raised in a letter from Qimiao Fan, the World Bank's Division Director for Kenya. The letter was addressed to Treasury Cabinet Secretary John Mbadi, Roads and Transport CS Davis Chirchir and Lands CS Alice Wahome.

The Bank said the project was incurring more than Ksh1.2 billion in additional costs every month. Contractors have not been given unrestricted access to the land, so construction cannot go ahead as planned.

The lender also listed several sections affected by the delays. It said only 1,281 of 1,669 project-affected persons had been compensated.

Commission lists progress by section

In its response, the NLC said it had verified assets on various sections of the highway. It put compensation so far at up to Ksh1.3 billion.

  • Isiolo–Kulamawe–Modogashe: Payments are ongoing. KeNHA is awaiting a World Bank no-objection approval to pay 1,280 PAPs a total of Ksh554.9 million.
  • Wajir–Kotulo: The NLC has approved Ksh824 million in compensation for 1,619 affected persons.
  • Isiolo–Kachuru: Ksh497 million has been approved for 296 PAPs.
  • Dimu–Elwak: Asset verification covering more than 1,105 PAPs has been carried out. The commission expects valuation to be completed by the end of November 2026.

The commission said these milestones showed its continued commitment to moving land acquisition and compensation forward on the project.

Court cases and insecurity cited

The NLC blamed several other factors for the delays. It said ongoing court battles over compensation were the main cause.

It also cited insecurity along the route, compensation offers that landowners have not collected, and landowners who could not be traced.

Completion date pushed back

The highway was 60 per cent complete as of October 26, according to Kenyans.co.ke. It was originally due for completion by January 2028, but the World Bank later moved the target to around 2030.

The road is a flagship part of the Horn of Africa Gateway Development Project. It is meant to improve connectivity across northern and north-eastern Kenya.