Kenya begins drilling at Turkana oil fields, targets first oil on 1 December
Kenya has formally started drilling for crude oil in Turkana County, with Gulf Energy E&P BV SEZ setting 1 December as the date for first oil production from the South Lokichar fields, according to Capital FM Kenya.
Energy and Petroleum Cabinet Secretary Opiyo Wandayi presided over the spudding of the company's Amosing 1 well pad. Spudding is the first stage of drilling a well and signals the official start of operations.
The ceremony marks the start of the first phase of Gulf Energy's US$6 billion drilling and production programme. It follows the recent rigging, levelling and commissioning of GW70, an onshore drilling rig leased from Great Wall Drilling Company at the Amosing 1 and 2 oil fields.
Project on schedule, says CS
CS Wandayi said development of the oil fields was running on schedule. He was accompanied by Roads and Transport Cabinet Secretary Davis Chirchir, East African Community Cabinet Secretary Beatrice Askul and other government officials.
Wandayi described the event as a turning point for the country. The spudding, he said,
"marks a historical milestone ahead of first oil production."
He also praised the professionalism of Gulf Energy and its contractors, saying they were working hard to meet the targets in the Field Development Plan (FDP) ratified by Parliament.
The government, he said, is supporting efforts to speed up development of Blocks T6 and T7 in line with the plan.
Production targets
Under the FDP's first phase, Gulf Energy is expected to concentrate on the Ngamia, Amosing, Twiga and Ekales fields, known together as NEAT. The target is more than 20,000 barrels per day.
Gulf Energy Managing Director Paul Limoh said the company's systems were ready. He said first-phase output will be moved by road to Mombasa from 1 December, where it will be stockpiled at the Kenya Petroleum Refineries Limited tank farms.
The company plans to raise output to 50,000 barrels per day in a second phase. Limoh said the firm was targeting six discoveries within Blocks T6 and T7, which have a best-estimate recovery of 326 million stock-tank barrels over a 25-year contract period.
For the first phase, Gulf Energy has hired Baker Hughes to provide integrated well services. SLB has been engaged to deliver the Early Production Facility.
Roads and regulation
CS Chirchir said the government is investing more than KSh24 billion in infrastructure, including roads, in the oil fields region. He said the investment would improve the area's social and economic standing.
Gulf Energy will run the fields under Production Sharing Contracts with the national government. The State Department of Petroleum and the Energy and Petroleum Regulatory Authority (EPRA) will provide oversight.
What kind of oil
According to the report, Kenya's crude is low in sulphur, asphaltene and aromatics but fairly high in wax. Its pour point is above ambient temperatures.
The oil is expected to be an intermediate, paraffinic, sweet crude with an API gravity of 30.5 degrees. It will be priced against Dated Brent. The associated gas is described as rich and sweet, though some areas have high carbon dioxide content.
Expected earnings
The government projects potential lifetime earnings of more than US$2.9 billion (about KSh371 billion) from the project. The final figure will depend on global oil prices and production volumes over the life of the fields.
Officials say the development will establish Kenya as a significant oil producer in East Africa.
More in Business
See all
Kenya Airways Seeks Three Senior Managers on Permanent Terms at Nairobi HQ

Truck Owners Down Tools at JKIA Expansion Site Over Ksh50M Unpaid Dues
.jpeg)
RareX to Challenge Mrima Hill Award to US-Led Consortium Over Alleged Late Bid

Lufthansa plans 1,000 job cuts at Frankfurt and Munich hubs amid losses

CBK opens one-year graduate internships, caps age at 29 with December 10 deadline







Global Community Remarks
0