Motorists using the busy Nairobi-Nakuru route could soon get relief from festive-season gridlock after the Transport Ministry said completed sections of the expanded Rironi-Naivasha road will be opened to traffic within the next four weeks, ahead of Christmas.

The ministry announced the plan in a statement on Saturday, November 21, saying it was speeding up construction on the wider Rironi-Mau Summit highway so that finished portions can be used before the holidays, according to Kenyans.co.ke.

Opening ahead of final finishing

Under the plan, the completed stretches will be handed over to motorists before the final layer of asphalt is laid. This means drivers will be able to use parts of the highway that have already been built while the remaining finishing works continue.

"Completed sections of the Rironi-Naivasha will be opened to motorists ahead of final asphalt finishing," the ministry said.

Transport Cabinet Secretary Davis Chirchir said motorists would be informed which sections are due to open, as well as the traffic arrangements that will be put in place to keep movement safe and orderly.

The Nairobi-Nakuru highway typically sees heavy traffic during the festive season, as thousands of travellers head upcountry and to other parts of the country. The ministry expects the partial opening to ease congestion along the corridor during that period.

Missed deadline

The announcement follows the government's failure to meet an earlier October 30 deadline to open the section to motorists. Kenyans had previously been assured that the works would be finished within a month and a half.

A day after that deadline passed, on October 31, Chirchir set out a revised timeline, saying the government was now aiming to complete the dualling works in December and allow traffic to resume on the highway.

About the project

The Rironi-Naivasha stretch covers 60 kilometres and is part of the larger 233-kilometre Rironi-Mau Summit Highway project. The route is a key link on the corridor connecting Kenya and Uganda.

Key details of the project, as reported by Kenyans.co.ke, include:

  • Cost: Ksh200 billion
  • Scope: Expansion of the existing road, with the Rironi-Naivasha section being upgraded to a four-lane road
  • Contractor: China Road and Bridge Corporation (CRBC)
  • Launch: Works officially began in November 2025
  • Completion target: June 2027

The upgrade is intended to handle the rising number of vehicles using the route. Once finished, the highway is expected to cut travel delays, improve road safety and make it easier to move passengers and goods between Nairobi, the Rift Valley and Western Kenya.

What motorists should expect

While the ministry has not yet named the specific sections to be opened, Chirchir indicated that further guidance would be issued to road users. Motorists planning to travel along the route over the holidays are advised to watch for official updates on which stretches are open and any diversions or traffic management measures in force.

The partial opening is likely to be closely watched given the earlier missed deadline and the high volume of traffic expected on the corridor in December.

This story was prepared by the Hamasta Newsdesk with AI assistance, based on reporting by Kenyans.co.ke. Read the original report. Photo: Kenyans.co.ke.