'We want fairness': MPs demand proof Kenyans are getting work on Sh154 billion JKIA upgrade as airport squeezes 10 million travellers into space for 7.5 million
More than 100 machines are already tearing into the ground at Jomo Kenyatta International Airport, but the MPs who went to see them on Tuesday wanted to know one thing: how many of the people and firms behind the Sh154 billion upgrade are Kenyan?
Members of the National Assembly's Transport and Infrastructure Committee, led by Ndia MP George Kariuki, toured the site and met the contractor, China Road and Bridge Corporation (CRBC), together with Aviation and Aerospace Development Principal Secretary Teresiah Mbaika and Kenya Airports Authority (KAA) Managing Director Moses Wekesa.
'Show us the evidence'
Limuru MP John Kiragu warned against foreign companies registering locally so they can win work meant for Kenyan businesses. "We want fairness. We need to see evidence to prove that you are engaging locals," he told the contractor, according to The Star and Nairobi News.
Kariuki urged CRBC to bring in more Kenyans so the country builds its own technical skills, and to use local materials and services instead of relying on imports.
MPs also asked why the procurement was moved from KAA, which runs the airport, to the Ministry of Roads and Transport. The reports do not record a detailed answer to that question.
An airport bursting at the seams
PS Mbaika told the committee the upgrade is long overdue. "We are currently receiving more than 10 million passengers annually when our capacity can only handle 7.5 million," she said. She added that Kenya was lagging behind its neighbours and that an airport master plan was developed in 2025 with stakeholders.
She said the State sought a new contractor after the Adani deal "faced challenges". The earlier plan with India's Adani Group was dropped after public protests. An open tender ran from March 3, 2026, and closed in May with two bidders. "We got two bidders, but CRBC emerged the best," Mbaika said. The contract is worth Sh154 billion, including tax.
What is being built and when
According to briefings reported by The Star, the Eastleigh Voice and Nairobi News, the project includes:
- Improvements to the existing runway and its exits.
- Upgrading the current terminal to handle 12 million passengers a year.
- A new taxiway serving both the domestic and international sides.
Construction is expected to take 18 months, with the whole project done within 36 months, putting completion in mid-2029. CRBC pointed to its work on the expansion of Bole International Airport in Addis Ababa and projects in Rwanda, Tanzania, Uganda and Dubai, and showed MPs a terminal design with a roof finish tailored for Kenya.
For travellers used to long queues and crowded halls at JKIA, the timeline means about three more years of a terminal working well beyond what it was built to handle.
Photos: Parliament of Kenya via The Star; The Eastleigh Voice. Thumbnail design: HAMASTA MEDIA.
More in Business
See all
SGR Passenger Numbers Fall 28 Per Cent in September as Revenue Drops by Ksh113m

PBO Proposes Three-Year Plan for Counties to Clear Ksh172.5bn Owed to Suppliers

KRA asks farmers selling to factories to use eTIMS reverse invoicing

Motorists Stranded for Hours as Gridlock Paralyses Nairobi-Mombasa Highway at Tsavo

Kenya Signs Ksh90bn Deal with Greek Firm for Floating LNG Power Plant in Mombasa







Global Community Remarks
0