Timboroa–Meteitei–Kopere road upgrade eases farmers' path to market
Farmers along the Timboroa–Meteitei–Kopere corridor are finding it easier to get their produce to buyers as works to upgrade the 63.2-kilometre road to bitumen standard near completion, according to Capital FM Business.
The project has reached 80 per cent physical progress against 74 per cent of the contract period elapsed. About 46 kilometres have been tarmacked so far, leaving 17.2 kilometres to be done.
The road starts at Timboroa Junction on the A104 and passes through Meteitei and Songor before ending at Kopere. It serves farming communities whose household incomes and local trade depend on moving farm inputs, harvests and other goods.
Easier trips to market
Samuel Karanja, who lives in Chagaya in Timboroa, Baringo County, told Capital FM Business that the improved road has removed many of the difficulties farmers once faced when taking vegetables, potatoes and other crops to market.
He has also found work on the construction project. He said the income helps him support his children.
Engineer Joseph Muange, who oversees the works, said the shift from gravel to bitumen is meant to improve access to farms and boost economic activity along the route. He pointed to the tractors and trucks carrying sugarcane that regularly use the corridor.
"It has provided access to the farms by the farmers and generally reduced the travel time," Engineer Muange said.
Ahead of schedule
Engineer Muange said the contractor is working ahead of the programme. He expects the works to be finished before the contractual deadline of 12 June 2027.
He said quality checks are built into every stage. Each finished construction layer is sampled and tested in a laboratory to confirm it meets contract specifications. Sections that fail are corrected before work moves on to the next stage.
After completion, the contract provides for a one-year defects notification period. This will be followed by three years of performance-based routine maintenance.
Jobs and roadside trade
About 200 technical staff and casual labourers have been employed during construction, giving households in the area an extra source of income.
The better road is also encouraging small businesses. Sheila Chepchirchir, who works on the project, said more traders have set up along the route, selling tomatoes, vegetables and potatoes to passing motorists.
For communities along the corridor, the main gains are cheaper and quicker access to farms, markets and customers. Local households are also earning wages from the construction work itself.
Key facts
- Length: 63.2 kilometres, from Timboroa Junction (A104) through Meteitei and Songor to Kopere
- Progress: 80 per cent physical works, with 74 per cent of contract time elapsed
- Tarmacked so far: 46 kilometres, with 17.2 kilometres remaining
- Contractual completion date: 12 June 2027
- Jobs created: about 200 technical and casual workers
- After completion: one-year defects period, then three years of performance-based maintenance
This story was prepared by the Hamasta Newsdesk with AI assistance, based on reporting by Capital FM Business. Read the original report. Photo: Capital FM Business.
More in Business
See all
Egypt nears $2.3bn IMF payout after staff-level deal on final loan review

Ship agents urge faster upgrades at Mombasa and Lamu ports to curb congestion

Treasury Lines Up Thika Road, Southern Bypass for Tolling Under PPP Plan
.jpeg)
StanChart Kenya pre-tax profit climbs 13pc to Sh14.9bn as fee income offsets rate squeeze

KRA explains how factories can issue eTIMS invoices on behalf of small-scale farmers







Global Community Remarks
0