NLC Revises Land List for Naivasha-Malaba SGR, Paving Way for Compensation Talks
The National Land Commission (NLC) has revised the list of land earmarked for compulsory acquisition along the planned Naivasha-Kisumu-Malaba Standard Gauge Railway, opening the door to compensation talks with affected landowners, according to Kenyans.co.ke.
The changes affect the SGR Phase 2B and 2C project, valued at about Ksh700 billion, and touch on landowners in Nakuru, Narok, Bomet and Kisumu counties.
In a Gazette notice dated November 20, the commission said it intends to acquire the parcels on behalf of the Kenya Railways Corporation (KRC), invoking Section 110 of the Land Act (Cap. 280).
Corrections to earlier lists
The latest notice amends previous lists, striking out parcels that had been included in error and adding others that had been omitted.
Among the changes, 59 parcels in North Mugirango Constituency, which an earlier notice dated October 9 had placed within the railway corridor, have now been removed from consideration.
What landowners must do
Residents of the affected areas have been invited to inspect plans of the land at the NLC offices at Ardhi House, 3rd Floor, Room 305, 1st Ngong Avenue, Nairobi. The plans are also available at the County Co-ordinator's offices in Narok, Kericho and Bomet during official working hours.
Anyone with a claim or interest in the listed land has been asked to appear in person before the commission on or before the official inquiry date. They must bring:
- A written claim for compensation
- A copy of their national identity card
- Their KRA Personal Identification Number (PIN)
- Documents proving ownership of the land
- Bank account details
Kenya Railways had earlier said it had set aside Ksh25 billion to compensate landowners whose property falls within the corridor.
Construction already under way
Work on the line has already started in Narok and on other sections of the route, with the contractor carrying out excavation, Kenyans.co.ke reported.
Kenya Railways Managing Director Philip Mainga has said the bulk of the project will be done by June 2027, allowing operations to start, while the remaining works are expected to wrap up in 2028.
Speaking to the press in October, Mainga described it as a two-year project and expressed confidence in its timeline.
"We expect that by June next year, we will be able to deliver most of the area for this project," Mainga said.
Expected benefits
Once finished, the railway will have stations in Narok, Kericho, Bomet, Nyamira, Homa Bay and Kisumu.
It is projected to carry up to 22 million tonnes of cargo every year, a capacity expected to reduce pressure on the roads and make it faster and more efficient to move goods between the interior and the port of Mombasa.
The extension builds on the existing SGR line, which already links Mombasa to Nairobi and Naivasha.
This story was prepared by the Hamasta Newsdesk with AI assistance, based on reporting by Kenyans.co.ke. Read the original report. Photo: Kenyans.co.ke.
More in Business
See all
NLC Rejects Blame for Isiolo-Mandera Highway Compensation Delays

Muhoozi Says Uganda Has Cancelled Ksh385bn SGR Deal, Raising Questions for Kenya

SGR land survey moves to Kibos and Chiga as Kisumu terminus plans take shape

SGR Passenger Numbers Fall 28 Per Cent in September as Revenue Drops by Ksh113m

Kenya Railways launches SGR car freight service: Mombasa to Nairobi in eight hours







Global Community Remarks
0