Treasury faces Sh109bn bill to revive stalled Arror, Kimwarer, Itare and Soin-Koru dams
The government will need to raise about Sh109.4 billion to complete four stalled multipurpose dams started under former President Uhuru Kenyatta, after Sh22.6 billion of public money had already been spent on them, according to Business Daily.
The Arror, Kimwarer, Itare and Soin-Koru dams carry a combined estimated cost of Sh132 billion. Budget disclosures show that by June 2026 none had passed 27 percent completion, with the least advanced at just eight percent.
The figures appear in sector budget proposals for the 2027/28 financial year, which list public projects that had stalled as at June 2026.
Ruto pushes diplomatic route
The disclosures come as President William Ruto tries to restart the projects through diplomatic talks, restructured financing and fresh deals with contractors. In April, during a three-day visit to Italy, he announced a breakthrough on Itare, following earlier agreements on Arror and Kimwarer.
Mr Ruto said the two countries had finally resolved outstanding issues and had "agreed on how we are going to implement this project going into the future."
Arror and Kimwarer
Arror Dam, launched in July 2017, had taken up Sh4.978 billion of its Sh38.5 billion budget, putting it at 13 percent completion. The State Department for ASALs and Regional Development says the project has stalled and that negotiations to resume work are under way. Completing the dam, meant to boost water storage and irrigation, will require a further Sh33.522 billion.
Kimwarer Dam, its sister project, is 12 percent complete after consuming Sh3.886 billion of an estimated Sh33.5 billion. The same department says talks to restart it are also ongoing, with Sh29.614 billion still needed.
Between them, the two dams have used Sh8.864 billion, leaving a balance of Sh63.136 billion on projects whose construction began close to nine years ago.
Work on both was halted amid corruption claims, procurement disputes and technical reviews questioning their viability. A technical team set up during the Kenyatta administration concluded that Kimwarer, as designed, was not technically or financially viable, while Arror was cleared to proceed.
The projects were tied to a complex financing arrangement involving private lenders, with Italian state-owned insurer SACE covering the risk of default. In December 2023, former Treasury Cabinet Secretary Henry Rotich and his co-accused were acquitted in the criminal case linked to the dams.
Itare contractor to stay on
Itare Dam in Kuresoi North, Nakuru County, is the most advanced of the four at 27 percent. It had absorbed Sh12.066 billion against an estimated Sh35 billion, leaving Sh22.934 billion outstanding.
Italian firm CMC di Ravenna, the original contractor, walked off the site in September 2018. Negotiations after Mr Ruto took office led to a settlement and a proposed restructuring under which CMC di Ravenna would remain the main contractor but subcontract the physical construction works.
Soin-Koru starved of funds
The Soin-Koru Multipurpose Dam has stalled at eight percent after spending Sh1.67 billion of its Sh25 billion budget. The State Department for Irrigation blames a lack of budgetary allocation, and says Sh23.33 billion is needed to finish it.
The dam is intended to tackle recurring floods in the Nyando basin while expanding irrigation and household water supply. It is designed to hold 93.7 million cubic metres of water, deliver 72,000 cubic metres a day, irrigate about 2,570 hectares and generate 2.5 megawatts of electricity.
Pressure on public finances
The combined Sh109.4 billion requirement lands on a Treasury already stretched by debt repayments and competing spending demands, Business Daily reports, underlining the cost of years of delays on the projects.
This story was prepared by the Hamasta Newsdesk with AI assistance, based on reporting by Business Daily. Read the original report. Photo: Business Daily.
More in Business
See all
Kenya seeks Sh20.3bn from private investors for Tana Delta rice project

US consortium open to listing 20% of Mrima Hill mining project on the NSE

Kenya Power warns households may pay more as its retail monopoly ends

KTDA leadership row escalates as Njeru accuses CEO Miano of defying court orders

Treasury, UNICEF report seeks to shield children's funding from Kenya's debt squeeze







Global Community Remarks
0